OPTIMIX Fast-setting Spalling System Adopted in Rapid Concrete Repair Work
2016-10-24

Hung Hom Cross Harbour Tunnel is one of the most congested roads between Kowloon and Hong Kong Island. The OPTIMIX fast setting spalling system has been adopted for concrete repair to the soffit areas along the northbound and southbound tunnels.

Each tunnel is 1.8 km in length and has been operated since 1972 and, as such, the soffit area for the lower ventilation duct has suffered from concrete deterioration. The rapid setting characteristics and desirable workability of the OPTIMIX product demonstrates its outstanding performance and has replaced the previous system of epoxy resin materials for concrete repairs. Product used:

•  OPTIMIX RM760